CPC G06F 9/485 (2013.01) [G06F 11/3428 (2013.01)] | 20 Claims |
1. A baseline monitoring method, comprising:
determining a plurality of tasks to be monitored in a baseline;
determining whether there is a first task to be monitored that has cyclic dependency according to dependencies among the plurality of tasks to be monitored, wherein the cyclic dependency indicates mutual dependency among the first tasks to be monitored;
determining a task instance to be checked for each of the tasks to be monitored, wherein in presence of the first task to be monitored that has cyclic dependency, for the first task to be monitored that is not a guaranteed task, determining the task instance to be checked for the first task to be monitored according to the cyclic dependency and dependency between the first task to be monitored and its downstream task to be monitored, and for a second task to be monitored that is not the guaranteed task, determining the task instance to be checked for the second task to be monitored according to dependency between the second task to be monitored and its downstream task to be monitored, wherein the second task to be monitored is a task to be monitored except the first task to be monitored, and the guaranteed task is a task added to the baseline by a user; and
for each of the tasks to be monitored, monitoring the baseline according to the task instance to be checked for the task to be monitored.
|