CPC A01B 79/005 (2013.01) [A01B 33/087 (2013.01); A01B 69/008 (2013.01); A01C 7/203 (2013.01); A01C 14/00 (2013.01)] | 43 Claims |
1. A method of mitigating compaction in a work area, the method comprising:
passing a vehicle through the work area at a plurality of reference points to generate compaction data for a compaction map;
determining the compaction map of the work area having the compaction data, wherein the compaction map comprises a first compaction level at a first reference point of the plurality of reference points and a second compaction level at a second reference point of the plurality of reference points that is less than the first compaction level;
passing a work tool through the work area at the plurality of reference points after determining the compaction map;
passing the work tool through the first reference point before passing the work tool through the second reference point;
adjusting the work tool at the plurality of reference points based on the compaction data of the compaction map;
initiating adjustment of the work tool at the first reference point associated with the first compaction level; and
terminating adjustment of the work tool at the second reference point associated with the second compaction level that is less than the first compaction level;