US 12,155,524 B2
Method for providing high availability service through gnb reallocation and device therefor
Kwangduk Jin, Suwon-si (KR); Daejoong Kim, Suwon-si (KR); and Hyunho Lee, Suwon-si (KR)
Assigned to Samsung Electronics Co., Ltd., Suwon-si (KR)
Appl. No. 17/626,291
Filed by Samsung Electronics Co., Ltd., Suwon-si (KR)
PCT Filed Jul. 6, 2020, PCT No. PCT/KR2020/008788
§ 371(c)(1), (2) Date Jan. 11, 2022,
PCT Pub. No. WO2021/010632, PCT Pub. Date Jan. 21, 2021.
Claims priority of application No. 10-2019-0084788 (KR), filed on Jul. 12, 2019; and application No. 10-2019-0129227 (KR), filed on Oct. 17, 2019.
Prior Publication US 2022/0271990 A1, Aug. 25, 2022
Int. Cl. H04L 41/0659 (2022.01); H04L 41/0663 (2022.01)
CPC H04L 41/0661 (2023.05) [H04L 41/0663 (2013.01)] 10 Claims
OG exemplary drawing
 
1. A method performed by a high availability service management device in a wireless communication system, the method comprising:
receiving, from a first gNodeB central unit (gNB-CU), in a first data center, a keep-alive message associated with available cell resources, wherein the keep-alive message includes logical gNB information, a number of operated cells, and a on service operation state;
in case that a reception of the keep-alive message fails a number of times for a given period of time, determining that a keep-alive message_failure has occurred;
identifying whether the keep-alive message failure is a simple path failure or an actual failure of the first gNB-CU via another entity interworking with the first gNB-CU;
based on the identification, determining a failure of the first gNB-CU in the first data center;
identifying whether there are available cell resources in the first data center;
in case that there are available cell resources in the first data center, relocating at least one logical-gNB in the first gNB-CU to a second gNB-CU in the first data center; and
in case that there are no available cell resources in the first data center, relocating at least one logical-gNB in the first gNB-CU to a third gNB-CU in a second data center,
wherein the second data center is different from the first data center,
wherein the at least one logical-gNB included in the first gNB-CU performs at least one function performed by the first gNB-CU, and