| CPC E21B 19/155 (2013.01) | 18 Claims |

|
8. A well system, comprising:
a rig floor;
a first rig floor robot positioned on the rig floor, wherein the first rig floor robot is configured to guide a lower end of a pipe stand towards a setback position on the rig floor;
a mast extending from the rig floor, the mast comprising a plurality of legs;
a pipe transport assembly slidably coupled to one of the legs of the mast, wherein the pipe transport assembly comprises an elevator configured to transport the pipe stand and which is pivotable relative to the mast about both a first pivot axis and a separate second pivot axis, wherein the second pivot axis extends orthogonally relative to the first pivot axis; and
a winch coupled to the mast and configured to raise and lower the pipe transport assembly along the mast.
|