1. A simulation device comprising:
a simulation section configured to simulate an operating status of a board work machine configured to perform predetermined board work on a board and produce a board product, and an operating status of an article moving device configured to supply an article needed for production of the board product to the board work machine based on a production plan of the board product; and
a calculation section configured to calculate a production stop time of the board work machine caused by a wait time from when production of the board product by the board work machine is stopped to when the article is supplied by the article moving device based on a result of simulation by the simulation section.
|