CPC F03D 13/10 (2016.05) [B63B 35/44 (2013.01); B63B 75/00 (2020.01); F03D 13/25 (2016.05); B63B 2035/442 (2013.01); B63B 2035/446 (2013.01); F05B 2240/93 (2013.01); F05B 2240/95 (2013.01)] | 25 Claims |
1. A method of installing an offshore wind turbine, the method comprising the step of:
raising a full-length tower for the offshore wind turbine by moving it longitudinally from a container in a floating substructure comprising a load-carrying device, the floating substructure being a support structure for the wind turbine; and
lifting equipment by the load-carrying device from a vessel to the floating substructure.
|