| CPC H02J 3/1892 (2013.01) [H02J 3/381 (2013.01); H02J 2300/28 (2020.01)] | 14 Claims |

|
1. A power plant controller for a renewable energy power plant comprising a plurality of renewable energy generators, the renewable energy power plant being connected to a power network, the power plant controller being configured to execute machine readable instructions to:
receive a signal indicative of a voltage level of the power network to which the power plant is connected;
receive a plurality of signals from the plurality of renewable energy generators, each signal being indicative of a voltage level of a respective renewable energy generator; and
determine, for each of the plurality of renewable energy generators, a respective reactive power set point by:
determining a reactive power reference value for that renewable energy generator based on an indicated voltage level of the power network;
determining a reactive power adjustment value for that renewable energy generator based on a difference between an indicated voltage level of that renewable energy generator and a reference voltage level determined based on indicated voltage levels of the plurality of renewable energy generators;
determining the reactive power set point for that renewable energy generator based on the reactive power reference value and the reactive power adjustment value, determined for that renewable energy generator; and
dispatch each determined reactive power set point to a respective local controller associated with the respective renewable energy generator for controlling that renewable energy generator.
|