| CPC G06F 9/466 (2013.01) | 18 Claims |

|
1. A data delay detection method, comprising:
obtaining a baseline construction parameter;
constructing a baseline instance according to the baseline construction parameter, wherein the baseline instance comprises a task link graph and a node parameter of each node in the task link graph, the task link graph is used to describe a data dependency relationship between at least two real-time tasks, different nodes in the task link graph are used to represent different real-time tasks, and the at least two real-time tasks are used to process a real-time data stream;
obtaining a data delay detection result of each real-time task; and
determining delay state characterization data of the baseline instance according to data delay detection results of the at least two real-time tasks, wherein
the baseline construction parameter comprises a task identifier of a baseline guarantee task, a baseline commitment delay, a baseline early warning delay, and a task delay gain coefficient, and
the constructing a baseline instance according to the baseline construction parameter comprises:
determining the at least two real-time tasks and the data dependency relationship between the at least two real-time tasks according to a pre-constructed task link relationship and the task identifier of the baseline guarantee task, wherein the task link relationship comprises the data dependency relationship between the at least two real-time tasks, and the at least two real-time tasks comprise the baseline guarantee task and a task that directly or indirectly provides data for the baseline guarantee task; and
constructing the baseline instance according to the at least two real-time tasks, the data dependency relationship between the at least two real-time tasks, the baseline commitment delay, the baseline early warning delay, and the task delay gain coefficient.
|