CPC G01R 31/396 (2019.01) [G01R 31/3842 (2019.01); G01R 35/00 (2013.01)] | 8 Claims |
1. A method for testing a cell monitoring unit, comprising:
applying respective cell voltages to cell voltage connections of the cell monitoring unit; and
carrying out a measurement on a cell monitoring unit which is in operation in order to determine whether a respective current is flowing via at least one cell voltage connection, and, when this is the case, outputting a fault message,
wherein measuring the current comprises interconnecting a current measuring apparatus without interruption in a current line leading to a respective cell voltage connection, further comprising:
connecting the current measuring apparatus initially in parallel with the current line; and then
opening a branch of the current line in parallel with the connections of the current measuring apparatus.
|