| CPC E02D 3/12 (2013.01) [E02D 5/46 (2013.01); E02D 37/00 (2013.01); E21D 9/001 (2013.01)] | 2 Claims |

|
1. A method of underground deployment, the method comprising the steps of:
drilling an underground bore through underlying geology;
lining the bore with a pipe;
passing equipment down the bore to a predetermined location;
using the equipment to make a hole at most only partially through the pipe at the predetermined location;
passing deployment equipment down the pipe to the predetermined location;
extending a probe through the hole, the probe configured to punch through the remaining pipe at the predetermined location; and
deploying material and/or equipment through the hole in the pipe into the underlying geology.
|