CPC B65G 53/16 (2013.01) [B01F 33/84 (2022.01); B01F 35/2112 (2022.01); B01F 35/2113 (2022.01); B28C 7/062 (2013.01); B65D 88/66 (2013.01); B65G 3/04 (2013.01); B01F 2101/28 (2022.01); B65G 2203/042 (2013.01)] | 18 Claims |
1. A method for operating a bulk material handling system, comprising:
measuring a height of dry bulk material disposed within one or more supply tanks;
transmitting the measurements of the height of the dry bulk material to a controller;
instructing a compressor, before, during or after measuring the height of the dry bulk material, to pressurize or aerate at least one of the one or more supply tanks;
transmitting instructions, before, during or after measuring the height of the dry bulk material, from the controller to a secondary controller disposed at each of the one or more supply tanks to:
actuate a first valve between first open and closed positions disposed upstream of each of the one or more supply tanks; and
actuate a second valve between second open and closed positions disposed downstream of each of the one or more supply tanks; and
activating a first vibration inducing device and a second vibration inducing device disposed at each of the one or more supply tanks, before, during or after measuring the height of the dry bulk material, at a frequency sufficient to dislodge dry bulk material stuck along the inside walls of the one or more supply tanks.
|