| CPC E21B 43/12 (2013.01) [E21B 23/01 (2013.01); E21B 29/06 (2013.01); E21B 33/12 (2013.01); E21B 43/14 (2013.01); E21B 49/0875 (2020.05)] | 6 Claims |

|
1. A method to reduce an inflow of water into an uncemented blank pipe, the method comprising:
analyzing, prior to the inflow of water from a formation into the blank pipe, wellbore data to estimate water cut of areas of the formation,
identifying areas of the formation with an estimated water cut of at least 50%,
detecting at least one portion of the blank pipe arranged in the identified areas of the formation with the estimated water cut of at least 50%,
actuating an alignment sub-system of an apparatus to align with the at least one portion of the blank pipe, and
actuating a plug sub-system of an apparatus to cover an opening in the at least one section of the blank pipe.
|