| CPC E02D 27/06 (2013.01) [E02D 27/34 (2013.01); E02D 27/36 (2013.01); E04H 9/02 (2013.01); E04H 9/14 (2013.01)] | 27 Claims |

|
1. A building development, having a building arranged on a building development base comprising, the building development base has a pontoon having at least one float for floating on a liquid and a pile mooring, wherein the pile mooring extends perpendicularly to the pontoon along a pile mooring axis through a passthrough opening of the pontoon,
further comprising the passthrough opening is configured centrally in the pontoon, and the pontoon is rotationally movably mounted around the pile mooring that extends through the passthrough opening, wherein the pontoon is alignable and positionable around the pile mooring axis, the pile mooring projects into a receiving chamber through the passthrough opening of the pontoon and through a first breakthrough arranged in a bottom of a receiving chamber arranged over the passthrough opening.
|