CPC E04H 12/16 (2013.01) [B66D 1/26 (2013.01); B66D 1/60 (2013.01); E04G 21/12 (2013.01); E04C 5/122 (2013.01); E04H 12/08 (2013.01); E04H 12/12 (2013.01); F03D 13/20 (2016.05)] | 22 Claims |
1. A method for introducing tensioning elements into a tower to a respective intended final position in which at least a given one of the tensioning elements is introduced into an interior space of the tower, connected to a pulling rope of a winch, and pulled into the tower in a direction from a bottom of the tower to a top of the tower by the winch, the method comprising the steps of:
placing on an upper end of the tower a mounting device with a boom rotatably mounted on a base frame;
aligning the boom with respect to a mounting position of the given tensioning element; and
pulling in and anchoring the given tensioning element to the upper end of the tower, wherein the pulling rope of the winch is guided above the mounting device.
|