| CPC E02F 5/226 (2013.01) [B01D 33/0353 (2013.01); B01D 33/804 (2013.01); B04C 5/14 (2013.01); B04C 5/28 (2013.01); B04C 9/00 (2013.01); E02F 3/8816 (2013.01); E02F 3/8891 (2013.01); E02F 3/907 (2013.01); E02F 3/925 (2013.01); E02F 3/9262 (2013.01); E02F 3/9268 (2013.01); E02F 3/9275 (2013.01); E02F 3/94 (2013.01); E02F 7/06 (2013.01); F04B 15/02 (2013.01); F04B 15/023 (2013.01); F04B 23/02 (2013.01); F04B 23/04 (2013.01); F04B 43/1253 (2013.01); B01D 45/16 (2013.01); B04C 5/26 (2013.01); B04C 2009/005 (2013.01); B07B 1/30 (2013.01); E02F 9/14 (2013.01)] | 20 Claims |

|
1. A method for hydro excavating a site with an excavation apparatus having at least three vessels for supplying and storing excavation fluid, the method comprising:
providing maiden water in a first vessel of the apparatus, the maiden water being at an initial level;
directing pressurized maiden water from the first vessel toward an excavation site, the pressurized water cutting earthen material;
removing cut earthen material and first cycle water from the excavation site;
separating first cycle water from the cut earthen material;
introducing the first cycle water into a second vessel, wherein a third vessel is selectively in fluid communication with at least one of the first vessel and the second vessel; and
introducing additional maiden water into the first vessel upon the maiden water level in the first vessel being reduced to below the initial level or less.
|