CPC E21B 43/281 (2013.01) [E21B 43/14 (2013.01); E21B 43/305 (2013.01)] | 17 Claims |
1. A modular solution mining method for use with a mineral deposit, the method comprising the steps of:
providing an injection wellbore, the injection wellbore including a horizontal injection portion, wherein the horizontal injection portion comprises a toe end and a heel end;
providing a production wellbore, wherein the production wellbore includes a horizontal production portion that is proximate to the toe end;
injecting a solvent into the horizontal injection portion;
generating a first turbulent solvent flow proximate to the toe end to generate a mineral solution and an initial first cavern proximate to the horizontal production portion;
motivating the mineral solution from the initial first cavern, into the horizontal production portion, and to a surface location;
placing a bridge plug into the horizontal injection portion between the toe end and the heel end; and
generating a second turbulent solvent flow, the second turbulent solvent flow being generated closer to the heel end than the first turbulent solvent flow and the second turbulent solvent flow generating a subsequent second cavern located in between the heel end and first cavern.
|