CPC B29C 63/06 (2013.01) [B29C 55/005 (2013.01); B29C 55/30 (2013.01); C09J 7/243 (2018.01); C09J 9/00 (2013.01); C09J 11/04 (2013.01); B29K 2101/12 (2013.01); B29L 2023/22 (2013.01)] | 11 Claims |
1. A method for manufacturing a reinforced pipe system for transporting a fluid, comprising:
contracting a thermoplastic pipe using a mechanical compression device;
wrapping or extruding a first fiber tape on a surface of the pipe while it remains at least partially contracted, said first fiber tape having continuous taut fibers;
securing ends of the first fiber tape to the ends of the pipe using a first heat source;
warming the first fiber tape and pipe using a second heat source;
embedding taut fibers into the pipe as the pipe is warmed; and
bonding the first fiber tape to the pipe as the first fiber tape and pipe reach a thermal equilibrium.
|