CPC F03D 80/85 (2016.05) [F03D 13/40 (2016.05); F05B 2230/61 (2013.01)] | 16 Claims |
1. A method of installing a power cable in a wind turbine tower, the method comprising:
arranging a section of the cable within the tower, the section having a length, greater than the tower height, by forming a cable loop within the tower, wherein an angle enclosed between a normal of a cable loop plane and the longitudinal direction of the tower is between 70° and 110°,
wherein forming the cable loop comprises lowering another part of the cable through an opening in a platform to form a lower portion of the cable loop.
|