| CPC B25J 9/026 (2013.01) [B25J 9/1005 (2013.01); B25J 9/1687 (2013.01); B25J 15/0066 (2013.01); B25J 15/0616 (2013.01); B25J 19/0008 (2013.01); B29C 70/388 (2013.01); B64F 5/10 (2017.01); G06K 7/10297 (2013.01); G06K 19/0728 (2013.01); B25J 9/104 (2013.01); B29L 2031/3082 (2013.01); B29L 2031/3085 (2013.01)] | 20 Claims |

|
1. A pick-and-place system for transferring and installing a contoured composite structure onto a mandrel, in a composite manufacturing system, the pick-and-place system comprising:
a tray station having a tray assembly designed to hold the contoured composite structure, prior to transfer and installation onto the mandrel; and
an installation station comprising:
the mandrel designed to receive the contoured composite structure, and designed to move along a moving manufacturing line, via a conveyor assembly; and
a pick-and-place assembly comprising:
a gantry assembly;
a main beam suspended from the gantry assembly, the main beam having a plurality of end effector assemblies and a pair of indexing assemblies, coupled to the main beam;
a vacuum system coupled to the main beam and coupled to the plurality of end effector assemblies;
a load balancer assembly coupling the main beam to the gantry assembly; and
a control system coupled to the pick-and-place assembly, to operably control the pick-and-place assembly.
|