Method and apparatus for layer-by-layer filling and compacting cohesive building materials in layers in boreholes
Rainer Dallwig, Potsdam (DE)
Assigned to JAMMY LIFE GMBH, Berlin (DE)
Appl. No. 17/780,978
Filed by JAMMY LIFE GMBH, Berlin (DE)
PCT Filed Nov. 26, 2020, PCT No. PCT/EP2020/083491
§ 371(c)(1), (2) Date May 28, 2022,
PCT Pub. No. WO2021/105276, PCT Pub. Date Jun. 3, 2021.
Claims priority of application No. 20 2019 004 885.5 (DE), filed on Nov. 29, 2019; application No. 20 2020 002 792.8 (DE), filed on Jun. 29, 2020; and application No. 10 2020 212 614.3 (DE), filed on Oct. 6, 2020.
Prior Publication US 2022/0412034 A1, Dec. 29, 2022
Int. Cl. E02D 3/08 (2006.01); C04B 24/26 (2006.01); C04B 28/00 (2006.01); E02D 3/068 (2006.01)
CPC E02D 3/08 (2013.01) [C04B 24/2641 (2013.01); C04B 28/001 (2013.01); E02D 3/068 (2013.01)] 13 Claims
OG exemplary drawing
 
1. A method for layer-by-layer filling and compaction of cohesive building materials, in particular of cohesive soil building materials, in at least one borehole near a surface, the method comprising:
introducing the cohesive building material into the at least one borehole; and
compacting the cohesive building material layer-by-layer using a conveying device including a push chain drive and a stuffing piston driven by means of the push chain drive.