| CPC G05B 15/02 (2013.01) [G06F 17/00 (2013.01); H05K 1/14 (2013.01); H05K 5/0256 (2013.01); H05K 7/14 (2013.01); H05K 7/1451 (2013.01); H05K 7/1468 (2013.01); H05K 7/1469 (2013.01); H05K 7/1474 (2013.01)] | 20 Claims |

|
1. A controller device in a building system, the device comprising:
a base comprising a first processor and a base interface, the first processor being configured to provide control operations in the building system; and
a first module installable on and removable from the base, the first module comprising first module interface for receiving power from and communicating with the base via the base interface and a terminal block; and
a second module installable on and removable from the base, the second module comprising a second module interface for receiving power from and communicating with the first module, wherein the first module acts as a serial pass-through to send address arbitration signaling to the second module.
|