| CPC E21B 43/36 (2013.01) [E21B 43/01 (2013.01)] | 20 Claims |

|
1. A control and management system of multiphase streams in subsea oil and gas production modules, the system comprising (i) a phase separator vessel; (ii) mixing lines; (iii) multiphase measuring instruments; (iv) flow rate, level, and pressure sensors; (v) a plurality of control valves; and (vi) cascade proportional-integral-derivative (PID) flow rate, level, and pressure controllers, wherein the multiphase measuring instruments indicate gas-liquid ratios that are configured to be used to command the flow rate controllers.
|