| CPC E02F 9/2029 (2013.01) [E02F 3/437 (2013.01); E02F 9/2045 (2013.01); E02F 9/261 (2013.01); E02F 9/265 (2013.01); G01G 19/083 (2013.01)] | 6 Claims |

|
1. A management apparatus for managing work of a shovel, the shovel including a lower traveling body, an upper turning body mounted on the lower traveling body, and an attachment attached to the upper turning body, the management apparatus comprising:
a hardware processor configured to calculate a weight of an excavation target to be excavated by the shovel, from a volume and a weight per unit volume of the excavation target before being excavated by the attachment, and calculate a number of transporter vehicles to be assigned a for carrying out the excavation target of the calculated weight, based on the calculated weight of the excavation target; and
a display device configured to display information on the calculated number of the transporter vehicles to be assigned.
|