| CPC D07B 1/062 (2013.01) [B60C 9/0007 (2013.01); D07B 2201/102 (2013.01); D07B 2201/104 (2013.01); D07B 2201/2006 (2013.01); D07B 2201/2009 (2013.01); D07B 2201/2066 (2013.01); D07B 2205/3025 (2013.01); D07B 2401/2095 (2013.01); D07B 2501/2046 (2013.01)] | 12 Claims |

|
1. A manufacturing method for a steel cord, wherein, the steel cord comprises:
a steel core wire located in a center and having a diameter of d;
M sheath-layer steel wires arranged around the steel core wire in the center, tangent to the steel core wire, and having a diameter of d1, at least two gaps L existing between the M sheath-layer steel wires, wherein M is 4;
d, d1, and L satisfy a relationship:
0.420<(d/d1)<0.800;
d1 is between 0.20 mm and 0.44 mm; and
L≥0.0008 mm;
wherein,
in a twisting process, a steel core wire and M sheath-layer steel wires are simultaneously unwound, an unwinding tension of the sheath-layer steel wires being equal, and the unwinding tension of the steel core wire being greater than that of each sheath-layer steel wire; and the steel core wire is placed in the center, and the M sheath-layer steel wires are uniformly distributed at 360° and bundled together around the steel core wire for twisting.
|