High level central plant optimization
Michael J. Wenzel, Oak Creek, WI (US); Robert D. Turney, Watertown, WI (US); Kirk H. Drees, Cedarburg, WI (US); and Matthew J. Asmus, Watertown, WI (US)
Assigned to Johnson Controls Technology Company, Auburn Hills, MI (US)
Filed by Johnson Controls Technology Company, Auburn Hills, MI (US)
Filed on Sep. 15, 2023, as Appl. No. 18/468,118.
Application 18/468,118 is a continuation of application No. 17/148,123, filed on Jan. 13, 2021, granted, now 11,774,948.
Application 17/148,123 is a continuation of application No. 16/214,984, filed on Dec. 10, 2018, granted, now 10,915,094, issued on Feb. 9, 2021.
Application 16/214,984 is a continuation of application No. 14/634,609, filed on Feb. 27, 2015, granted, now 10,175,681, issued on Jan. 8, 2019.
Claims priority of provisional application 61/987,361, filed on May 1, 2014.
Prior Publication US 2024/0061404 A1, Feb. 22, 2024
This patent is subject to a terminal disclaimer.
Int. Cl. G05B 19/418 (2006.01); G05B 13/04 (2006.01); G05B 15/02 (2006.01); G06N 20/00 (2019.01); G06Q 10/04 (2023.01); G06Q 10/06 (2023.01); G06Q 50/06 (2012.01)
CPC G05B 19/418 (2013.01) [G05B 13/048 (2013.01); G05B 15/02 (2013.01); G06N 20/00 (2019.01); G06Q 10/04 (2013.01); G06Q 10/06 (2013.01); G06Q 50/06 (2013.01); G05B 2219/2639 (2013.01); G05B 2219/2642 (2013.01); G05B 2219/31414 (2013.01); G05B 2219/32021 (2013.01); Y02P 70/10 (2015.11); Y02P 80/10 (2015.11)] 20 Claims
OG exemplary drawing
 
1. A controller for equipment that operate to provide heating or cooling to a building or campus, the controller comprising:
a processing circuit configured to:
obtain an objective function that expresses a control objective as a function of an amount of one or more input resources consumed by the equipment at each of a plurality of time steps of an optimization period;
determine a relationship between (i) the amount of the one or more input resources consumed by the equipment and (ii) an amount of one or more output resources produced by the equipment as a result of consuming the one or more input resources;
optimize the objective function over the optimization period, and subject to a constraint based on the relationship, to determine a distribution of production of the one or more output resources across the equipment at each of the plurality of time steps; and
operate the equipment to achieve the distribution at each of the plurality of time steps.