Method for underground separation of components in sulfur-containing flue gas and sequestration of carbon dioxide and sulfides
Fuzhen Chen, Qingdao (CN); Shengnan Wu, Qingdao (CN); Shihao Liu, Qingdao (CN); Yuhang Zhou, Qingdao (CN); Yixuan Liu, Qingdao (CN); Yan Tian, Qingdao (CN); and Jianwei Gu, Qingdao (CN)
Assigned to China University of Petroleum (East China), Qingdao (CN)
Filed by China University of Petroleum (East China), Qingdao (CN)
Filed on Aug. 20, 2024, as Appl. No. 18/809,324.
Claims priority of application No. 202410206997.X (CN), filed on Feb. 26, 2024.
Int. Cl. E21B 41/00 (2006.01); B01D 53/50 (2006.01); B01D 53/52 (2006.01); B01D 53/62 (2006.01); B01D 53/78 (2006.01)
CPC E21B 41/0064 (2013.01) [B01D 53/507 (2013.01); B01D 53/523 (2013.01); B01D 53/526 (2013.01); B01D 53/62 (2013.01); B01D 53/78 (2013.01); B01D 2251/402 (2013.01); B01D 2251/404 (2013.01); B01D 2252/103 (2013.01); B01D 2257/302 (2013.01); B01D 2257/304 (2013.01); B01D 2257/504 (2013.01); B01D 2258/0283 (2013.01)] 7 Claims
OG exemplary drawing
 
1. A method for underground separation of components in sulfur-containing flue gas and sequestration of carbon dioxide and sulfides, characterized by comprising:
injecting sulfur-containing flue gas into an injection well which is arranged in a well pattern of a sequestrated aquifer in advance, the formation water of the sequestrated aquifer being neutral or slightly alkaline, the injection pressure being smaller than or equal to a first preset pressure upper limit, and the well pattern being of a one-injection and one-production well pattern structure arranged in the sequestrated aquifer and forming one-dimensional linear flow or semi-one-dimensional linear flow;
transiting and injecting formation water into the formation at a first preset injection speed by an injection well of the well pattern after injecting the sulfur-containing flue gas for a first preset time, maintaining the first formation pressure, and conducting water drainage and gas production by a production well of the well pattern in a mode of a fixed bottom hole flowing pressure, the first preset pressure upper limit being 44.5 MPa;
and determining the well shut-in time according to the nitrogen molar concentration of the production well and conducting well shut-in;
wherein, the step of injecting sulfur-containing flue gas into an injection well which is arranged in a well pattern of a sequestrated aquifer in advance, comprises:
injecting sulfur-containing flue gas into an injection well which is arranged in a well pattern of a sequestrated aquifer in advance, and meanwhile conducting water drainage operation by a production well of the well pattern in a mode of a fixed bottom hole flowing pressure, the injection pressure being less than or equal to 44.5 MPa, and the duration of injecting the sulfur-containing flue gas being 58 days.