CPC H04L 67/1008 (2013.01) [H04L 67/1004 (2013.01); H04L 67/12 (2013.01); G05B 19/4184 (2013.01); G05B 19/41865 (2013.01)] | 14 Claims |
1. A process management method that is performed by a smart process system including a main server, a plurality of process servers, a worktable, and a plurality of process display terminals arranged on the worktable in order of process and respectively connected to the plurality of process servers and is capable of changing a process line, the process management method comprising:
(a) detecting, by one server of the plurality of process servers involved in performing a current process, stop of process progress due to a server different from the one server being down;
(b) transmitting a process command signal to a another process server by the one server; and
(c) providing, by the another process server, process work information of a work after the process progress is stopped to a process display terminal connected to the another process server based on the process command signal,
wherein the main server and the plurality of process servers each include a plurality of process DB areas independently allocated for each process.
|