CPC E21B 23/03 (2013.01) [E21B 19/22 (2013.01); E21B 29/002 (2013.01); E21B 33/04 (2013.01); E21B 33/0422 (2013.01); E21B 33/06 (2013.01)] | 20 Claims |
9. A method, comprising:
installing, prior to installation of a blowout preventer (BOP), a tubing head spool (THS), the THS having first inner diameter larger than or equal to a second inner diameter of the BOP;
landing, on a well after installation of the THS, the BOP;
running, through both the THS and the BOP, one or more strings to conduct a wellbore operation;
installing, through the BOP, an orientation sleeve within the THS, the orientation sleeve having a body outer diameter that is less than both the first inner diameter and the second inner diameter; and
landing, through the BOP, a tubing hanger.
|