US 11,720,839 B2
Project planning system
David A. Scholar, Newport Beach, CA (US)
Assigned to GreenGo Systems, Inc., Newport Beach, CA (US)
Filed by GreenGo Systems, Inc., Newport Beach, CA (US)
Filed on Oct. 25, 2021, as Appl. No. 17/510,112.
Application 17/510,112 is a continuation of application No. 14/985,280, filed on Dec. 30, 2015, granted, now 11,157,848.
Application 14/985,280 is a continuation of application No. 12/690,026, filed on Jan. 19, 2010, abandoned.
Claims priority of provisional application 61/177,961, filed on May 13, 2009.
Claims priority of provisional application 61/145,503, filed on Jan. 16, 2009.
Prior Publication US 2022/0156659 A1, May 19, 2022
Int. Cl. G06Q 10/0631 (2023.01); G06Q 10/101 (2023.01); G06Q 10/10 (2023.01); G06Q 50/08 (2012.01); G06Q 50/18 (2012.01); G06Q 10/06 (2023.01); G06Q 30/0601 (2023.01); G06Q 50/00 (2012.01); G16H 10/20 (2018.01); G16H 15/00 (2018.01)
CPC G06Q 10/06313 (2013.01) [G06Q 10/06 (2013.01); G06Q 10/06315 (2013.01); G06Q 10/101 (2013.01); G06Q 10/103 (2013.01); G06Q 30/0611 (2013.01); G06Q 50/01 (2013.01); G06Q 50/08 (2013.01); G06Q 50/188 (2013.01); G16H 10/20 (2018.01); G16H 15/00 (2018.01)] 20 Claims
OG exemplary drawing
 
1. A method of collaboratively generating a virtual project portfolio for a construction project comprising using a non-transitory computer useable medium having computer readable instructions embodied therein, wherein the computer readable instructions cause a computer to:
receive first construction project information inputs about the construction project from a first user interface, wherein the first construction project information inputs include a type of construction and a space in a structure included in the construction project;
select a first set of filters from a plurality of filters stored in memory to obtain information relating to the space based on at least the type of construction and the space in the structure included in the construction project received in the first construction project information of information from the first user;
generate a first portion of the project portfolio on the memory, wherein the first portion of the project portfolio comprises a vision album comprising the construction space information obtained from at least one database maintained in the memory using the first set of filters selected using the first construction project information inputs, wherein the vision album comprising the construction space information includes a first list of professionals based on the first construction project information inputs;
provide the first portion of the project portfolio to the first user interface to allow the first user interface to modify the first portion of the project portfolio and to select a first professional from the first list of professionals;
receive first selection information inputs from the first user interface, wherein the first selection information inputs include a selection of the first professional from the first list of professionals;
grant access to the first portion of the project portfolio to the selected first professional;
notify the selected first professional that second construction project information inputs must be provided via the second user interface;
provide the first portion of the project portfolio to the selected first professional via a second user interface in response to the selection of the selected first professional from the first user interface;
receive second construction project information inputs from the second user interface; modify the first portion of the project portfolio using the second construction project information inputs received from the second user interface;
generate a second portion of the project portfolio on the memory comprising a second list of professionals based on the modified first portion of the project portfolio, wherein the second list of professionals is different than the first list of professionals;
provide the second portion of the project portfolio to the second user interface to allow the second user interface to modify the first portion of the project portfolio and to select a second professional from the second list of professionals;
receive second selection information inputs from the second user interface, wherein the second selection information inputs includes a selection of the second professional, different from the first professional, from the second list of professionals;
grant access to the first portion of the project portfolio to the selected second professional;
notify the selected second professional that third construction project information inputs must be provided via the third user interface;
provide the second portion of the project portfolio to the selected second professional via a third user interface in response to the selection of the selected second professional from the second user interface;
receive third construction project information inputs from the third user interface to allow the third user interface to modify the first portion of the project portfolio; and
modify the first portion of the project portfolio using the third construction project information received from the third user interface.