CPC G06F 11/3006 (2013.01) [G06F 11/3404 (2013.01); G06F 11/3428 (2013.01); G06F 11/3433 (2013.01)] | 20 Claims |
1. A method comprising:
monitoring data processing efficiency information for a cluster deployed with a first configuration in a computing environment, wherein the data processing efficiency information comprises a score indicative of a relationship between a data processing rate of the cluster to a physical resource allocation to the cluster;
determining when the data processing efficiency information meets at least one criterion to transition the cluster from the first configuration to a second configuration;
in response to the data processing efficiency information meeting the at least one criterion, identifying an optimized configuration for the cluster; and
implementing the optimized configuration to modify the cluster to the second configuration.
|