US 11,943,120 B1
Handling of backlogged data center asset telemetry information
Venkata B. Donepudi, Round Rock, TX (US); and Sudhir Vittal Shetty, Cedar Park, TX (US)
Assigned to Dell Products L.P., Round Rock, TX (US)
Filed by Dell Products L.P., Round Rock, TX (US)
Filed on Oct. 24, 2022, as Appl. No. 17/971,782.
Int. Cl. H04L 43/04 (2022.01); H04L 41/147 (2022.01)
CPC H04L 43/04 (2013.01) [H04L 41/147 (2013.01)] 11 Claims
OG exemplary drawing
 
1. A computer-implementable method for performing a data center asset telemetry operation, comprising:
monitoring telemetry information for a plurality of data center assets;
determining whether any of the telemetry information includes backlogged telemetry aggregation information;
performing a telemetry aggregation operation when the telemetry aggregation information is backlogged, the telemetry aggregation operation collecting and aggregating the backlogged telemetry aggregation information; and,
dividing the backlogged telemetry aggregation information into segments based upon at least one of a time series segment size and a standardized segment size; and wherein
a time series forecasting approach is used to process a past number of telemetry information segment transfers;
the backlogged telemetry aggregation information is divided into segments based upon a forecasted data transfer rate; and
the forecasted data transfer rate is determined from an average of a plurality of successful telemetry information transfer segments.