CPC G05B 23/0272 (2013.01) [G05B 23/0283 (2013.01); G06N 7/01 (2023.01)] | 20 Claims |
1. A computing system comprising:
a communication interface;
at least one processor;
an asset data platform;
a non-transitory computer-readable medium;
and program instructions stored on the non-transitory computer-readable medium that are executable by the at least one processor such that the computing system is capable of:
deriving a respective failure probability for each asset of a set of assets operating in a substation;
determining an electrical configuration of the substation;
determining a failure probability of the substation based on (i) the respective failure probability for each asset of the set of assets and (ii) the electrical configuration of the substation;
and presenting a visualization that comprises: a visual representation of the determined failure probability of the substation, and
a visual representation of one or more of (i) the respective failure probability for each asset of the set of assets operating in the substation, or (ii) the determined electrical configuration of the substation;
wherein the presenting is performed utilizing the asset data platform;
wherein the visualization comprises: a navigable view and one or more selectable items related to the failure probability of the substation; and
wherein in response to the asset data platform receiving an indication of a selection of the one or more selectable items, additional information related to the failure probability of the substation is presented by the asset data platform.
|